This report will be published in a Supplementary Papers pack.
Minutes:
The Board received an update with respect of progress in delivery of the Levelling Up Fund (LUF) projects (LUF0297) in Bromsgrove Town Centre between April and August 2022. The two projects were taking place at Windsor Street and the former Market Hall site.
The Board was first updated on the Windsor Street Site (former Fire Station at Windsor Street).
The Leader of the Council addressed the Board, explaining that the Windsor Street site had stood empty for more than six years and interest had been expressed in the site for some time. The District Council purchased the full site from the Herefordshire and Worcestershire Fire and Rescue Service (HWFRS) and Worcestershire County Council (WCC) before the end of the 2021/22 financial year at a cost of £1.806m. It was noted the purchase price for the site was below the original asking price of £2.4m, and the acquisition was necessary to enable the start of feasibility works.
The Head of North Worcestershire Economic Development and Regeneration confirmed that the District Council needed to acquire freehold of the full site before a site feasibility study could be undertaken. Members were informed that the site was purchased from other public agencies, meaning the transaction was cost-neutral to the taxpayer.
The Head of North Worcestershire Economic Development and Regeneration clarified that the aim of the Windsor Street site redevelopment was to deliver residential-led mixed housing which was proposed to include 29 town houses. It was confirmed that the residual land value stood at £1.90m (as of April 2022).
It was reported that pre-development remediation works were taking place at the former Fire Station in Windsor Street. An intrusive ground investigation (phase II) report was submitted to the Environment Agency (EA). The EA agreed with the findings of the report but requested a further ground contamination water sampling at the Spadesbourne Brook, which was undertaken by the consultants in August.
In addition, a detailed quantitative risk assessment (DQRA) and draft remediation strategy were currently in the final preparation stages before submission to the EA.
Members were assured that building works would not commence on the Windsor Street site until the remediation strategy and the environmental method statement had been fully approved by the EA.
Following the update on the Windsor Street Site, Members asked for clarification with regards to some of the areas highlighted and provided a number of comments as follows:
The Board subsequently received an update on the former Market Hall site project.
The Head of North Worcestershire Economic Development and Regeneration addressed the Board and stated that the development of the Market Hall site required caution as part of the site was in a conservation area and with a landmark building adjacent. It was noted that the main risk to the project’s delivery remained cost, especially considering the current inflationary pressures.
It was recalled that the results of the survey of the creative business sector on the preferred uses for the Market Hall site showed support for several uses including multifunctional community space, creative studios, and workshop spaces. The soft market testing undertaken in July 2022 for appointment of a design team confirmed interest in the West Midlands for flexible workspaces and commercial support behind such proposals.
It was noted that the original recommendation of the technical advisor for the former Market Hall project was to proceed with a two-stage design and build contract from feasibility (RIBA stage 2) with a contractor-led design team. However, following the request of the Levelling Up Programme Board in August for a review of the route to procurement, the advice was updated. It was now recommended that a multidisciplinary design team (Multi-dis DT) be appointed, as opposed to a contractor-led design team, from RIBA stage 2. This had enabled the Council to avoid entering into early agreement with a contractor and provided time to develop the project brief to a sufficient level before being released to the market.
The Head of North Worcestershire Economic Development and Regeneration stated that there was a tight planning submission deadline for the site of March 2023, meaning that public engagement would need to commence immediately following the appointment of a multi-disciplinary design team in December 2022.
In relation to discussion on the Market Hall site, Members asked several questions and the following responses had been provided:
RESOLVED that the update be noted.
Supporting documents: