The Regeneration Project
Delivery Manager updated the Board on the levelling up fund Windsor
Street and Nailer’s Yard projects.
The following key points were
raised:
Windsor Street:
a)
Phase Two remediation required six months for
treatment and six months for monitoring works.
b)
Cabinet had agreed the site redevelopment for
housing via partnership with a Registered Social Landlord
(RSL).
Nailer’s Yard:
a)
Construction was progressing with completion
expected in May 2026.
b)
Bruton Knowles had been appointed as property
management agent for the commercial building.
.
c)
The Pavilion building operational model was under
review.
Members questions and comments
were as follows:
Windsor Street:
- What were the
timeframe and costs for the groundwater treatment options as
suggested feedback from Environment Agency (EA)? Officers explained the timeframe for Phase One and
Phase Two as detailed in the report and
also reassured Members that although works would take six
months for treatment works and six months for monitoring, there
would be continuing progression with the project in other areas,
such as applying for planning permission. Members were also advised that the works would be
within budget for Phase Two remediation works.
- Members requested
that the Board be included in updates for the RSL options, prior to
Cabinet considerations. Further
discussions were also raised that considerations for a local
provider may be more beneficial for residents, particularly when
reporting issues. In response the
Executive Director explained that the options for selecting the
suitable contractor was in progress, however, local needs would be
a consideration.
Nailers Yard Site:
- Members noted that
property agents Bruton Knowles had been appointed to undertake the
property management of the commercial building but requested
clarity on who would manage the Pavilion Buildings. In response the Board was advised that an
operational model was being put in place to explore options such as
managing inhouse and considerations for third party
involvement.
- Concerns were raised
that GJS Dillon were continuing to receive enquiries for the
commercial building, but no tangible lettings had been
received. It was explained that due to
delays in appointing Bruton Knowles, there had been some delays
with progression, however, Officers were hopeful that an update
could be provided at the next meeting in February 2026.
- An update with
regards to progression with the release of the restrictive covenant
was also requested by Members. It was
explained by the Leader that conversations were in progress to
escalate the matter and that an update would be provided to the
Board. Further discussions continued
with Members suggesting that delays with the progress of the
covenant release
and operational management of the Pavilion should be
included as a risk to the Council which was noted by
Officers.
- Members also
requested an update on progress for the culvert works and costs
associated for the project. Officers
informed the Board that works to the culvert were progressing as
per the current programme (4th May completion). Weather
conditions may lead to delays due to the works being carried out in
winter. The project manager explained that one complaint had been
received from a local resident about the noise from the
pumps but this was now resolved with
Kier installing acoustic fencing.
The Leader and Officers
concluded discussions and were pleased to inform the Board that a
representative from the Ministry of Housing, Communities and Local
Government (MHCLG) had visited Windsor Street and Nailers Yard
site. The representative provided positive feedback, noting that
the works were progressing well and highlighted that having a set
completion date was a significant achievement when compared to
progress made by other Local Authorities.
RESOLVEDthat the
update on the progress of the Levelling Up Fund projects be
noted.