The Regeneration Project Delivery Manager
presented an update on the Levelling Up Fund Programme in
Bromsgrove to the Board.
Members were informed that there was a
typographical error within the report at point 3.8 of the table
under ‘Risk and fixed price allowance’ and that the
figure stated should have read £58,151.08 and not
£55,151.08 as recorded.
The following key points were discussed with
the Board:
Windsor Street
-
Brownfield Solutions had completed Phase One of
remediation works. The Environment Agency (EA) technical feedback
was expected to be completed in October 2025.
-
Once feedback from the EA was received, the Council
was likely to undertake Phase Two remediation works, with a budget
allowance in place to cover the costs.
Completion was expected by May 2026.
-
Cabinet was due to consider housing delivery options
in November 2025.
Nailers Yard
-
Works to the culvert had increased to £1.6m,
with a provisional sum allowance of approximately £225,000 in
the Kier contract. This had increased the overall Levelling Up
Programme costs by £165,000. Therefore, an urgent decision
was taken in August 2025 to commit a further £500,000 to the
Levelling Up Programme, which included an allowance of
£335,000 for additional contingency.
-
The completion date was originally expected to be
January 2026; however, this had been extended to 4th May
2026.
-
There had already been strong commercial interest in
the office space and food and beverage units in the commercial
building with service charge arrangements in progress.
-
The Full Business Case (FBC) to secure the
Council’s funding from the former Greater Birmingham and
Solihull Local Enterprise Partnership (GBSLEP) was in
progress.
-
The overall funding secured of £16.103 million
had increased by £1.093 million to a total of £17.194
million including the additional £500,000 agreed by BDC which
increased the total to £17.694 million. The final cost would be an estimated £19.8
million. The GBSLEP bid for
£2.425 million was pending.
Therefore, the total potential funding pot was £20.118
million.
-
There were risks reported with a potential impact on
project budget and programme at the Nailers Yard site for culvert
works, incoming electrics and the commercial building
layout. Potential risks were also
highlighted at the Windsor Street site for EA sign off of
remediation works and BDC were due to agree future delivery options
for the site prior to any works.
Following the levelling up update, Members discussed
a number of points:
-
Assurance on the completion date was discussed, due
to the delays arising from culvert works. It was explained that any delays caused by the
client or beyond anyone’s control, such as poor weather,
would be met by the Council whereas any delay based on contractor
performance would be applied to the contractor Kier Construction
Limited.
-
Service charge explanations and concerns were
discussed with the Board. Officers reassured Members that a
resolution to secure the leases with incoming tenants would be a
priority.
-
Clarification on a cost breakdown was discussed for
Mechanical and Electrical (M&E) works, prolongation, insurance
and overheads. Officers agreed that a
more detailed breakdown would be provided to Members.
-
Return on investment was also discussed with the
Board and Officers provided details of the six-year payback
claim.
-
Clarification on the specifics of spend for the
GBSLEP funding were also discussed with details provided to the
Board.
-
Further information about housing density at the
Windsor Street site was discussed and Members were informed that a
meeting was scheduled with the Principal Conservation Officer to
review the options available.
-
Members were provided with an explanation of the
culvert works as requested. It was noted that the works were deemed
necessary to mitigate flood risks and that omitting them would have
significantly increased the risks.
-
Revenue expectations were discussed, with an
estimated annual income of £330,000 to the Council. It was
explained that service charges covered building upkeep, while voids
liability remained with the Council.
-
Members were also given clarification on what
service charges entailed and it was explained that it applied to
the property management. The Board was informed that the
appointment of a property management agent had been delayed due to
the procurement process, but progress was being made.
-
Homes England funding for Windsor Street was also
discussed with Members querying if any restrictions
applied. It was explained that
additional affordable housing provision could attract funding
opportunities.
RESOLVED that
the update on the progress of the Levelling Up
Fund projects be noted.</AI9>
(During
consideration of this item, Members discussed matters that
necessitated the disclosure of exempt information. It was therefore
agreed to move to exclude the press and public prior to any debate
on the grounds that information would be revealed that included
information relating to the financial or business affairs of any
particular person (including the authority holding that
information). However, there is nothing
exempt in this record of the meeting).