The Regeneration Project
Delivery Manager presented the Levelling-Up Fund Programme –
Quarterly Update to the Board as follows:
-
The Windsor Street site was discussed and as of the
15th of January, all the buildings on the site had been
demolished. The removal of the gas pipe
in November had added a six-week delay to the project and incurred
City Demolition’s standing time costs which were agreed at
circa £118k.
-
Brownfield Solutions had reviewed the contaminated
materials and installed monitoring wells as part of the remediation
strategy. Ground water monitoring had
commenced in February 2025 and would continue until mid-August
2025.
-
Further to the testing of two zones for contaminated
material detecting 14 exceedances, the programme would be extended
due to the analysis turnaround time.
-
Thomas Lister had been appointed to support with the
development appraisal that would inform the options paper. Officers
had also engaged with Homes England to discuss potential funding
streams, if the Council decided to develop the site. Homes England confirmed that they could only
provide funding for affordable housing above the policy
requirements.
-
Whilst the gas pipe removal added a six-week delay
to the demolition programme, the project was continuing to progress
in line with timescales and remained to be on track to be delivered
by January 2026.
-
The
key risks affecting the project were contaminated land with further
investigations required during the works, working adjacent to
occupied buildings and right of way (easement across
site).
-
The Public Realm Works site was
discussed. Worcestershire County
Council (WCC) were responsible for the design and delivery of the
Public Realm element of the project, given their statutory
responsibilities. Final prices were agreed and linked to a
Memorandum of Understanding (MOU) that existed between Bromsgrove
District and Worcestershire County Councils who were delivering the
works.
-
Both the works on the High Street and on Chapel
Street had been completed with an updated Risk Register provided to
Members.
-
The Council had requested a lesson learned workshop
to be held with WCC.
-
The
Former Market Hall Site was discussed.
The main contract with Kier was signed on 29th October
2024. The main construction programme
had commenced in November 2024. Piling
was completed at the end of December 2024 and groundworks had
commenced in January 2025.
-
During the Pre-Construction Services
Agreement (PCSA), significant quantities of ground obstructions
were discovered, leading to delays in the formal commencement of
the main contract.
-
Minor delays of six weeks had been
incurred due to ground obstructions and Kier had formally submitted
a claim for ground obstructions, loss and expenses. The QS from Arcadis had reviewed the claim and
considered it reasonable.
-
Kier had provided the cash flow
forecast. Whilst the programme had a
revised end date of January 2026, the Levelling-UP Fund (LUF)
monies would be spent by the September 2025 deadline. Officers had also received confirmation that BDC
had an extension period until the end of March 2026 to spend the
LUF money.
-
In January, the LUF Board agreed to
directly appoint Arcadis to provide employer agent and quantity
surveyor (QS) services for RIBA stage 5. Following a recommendation
from the project manager, it was agreed that carrying out a
procurement exercise would carry too much risk as another supplier
may not provide a lower fee proposal.
Due to the value of the contract, an urgent decision was
taken.
-
A Clerk of Works was appointed on
behalf of the Council and would carry out site inspections twice a
month for building works and for mechanical and engineering
(M&E) works.
-
The project team had held a design
meeting to agree the layout of the commercial building. It was
agreed that the first and second floor office space would be split
into two units, following advice from local agents, GJS Dillon.
-
Following a procurement exercise, GJS
Dillon had been appointed as the agents for the commercial building
who would be preparing a marketing strategy and advertise the space
as well as handle lettings on behalf of the Council. This was
agreed by LUF Board Members in December 2024.
-
The project team were preparing an Expression of
Interest (EOI) to Birmingham City Council for the Greater
Birmingham and Solihull Local Enterprise Partnership (GBSLEP)
monies totalling £2.45m. Following the EOI being accepted,
the project manager would prepare the full business case for
submission. However, BDC were informed
that Birmingham City Council were unable to provide any Local
Authority funding until 2026/2027 financial year, therefore, BDC
may be required to utilise short-term borrowing to complete the FMH
project until funding could be drawn down.
Following consideration of the item, the Board made
the following comments:
-
When would the right of access be reinstated on
Windsor Street? – In response it was advised that City
Demolition were preparing quotes for reinstatement.
-
If statutory responsibilities between the Council
and Worcestershire County Council could be formerly agreed and
considered.
-
What the additional costs for provisional sums and
contingency included in the project budget were referring to?
– The Board noted that this was in relation to predicted
budget fees. A fees and tracker survey
carried out in 2022 reviewed the professional fees incurred such as
design, architecture and list surveys.
The original budget for RIBA 5 and 6 services for Arcadis QS was
set at £180k, however the revised fee was for approximately
£220k. Officers were confident
that there shouldn’t be a necessity for any further surveys,
however, contingencies were in place.
-
Members expressed concerns that Birmingham City
Council were unable to provide any Local Authority funding until
2026/2027 for the Greater Birmingham and Solihull Local Enterprise
Partnership (GBSLEP) monies and that the Council may be required to
consider utilising short-term borrowing to complete the FMH project
until funding could be drawn down. Members had raised concerns
during previous meetings but had been reassured that withdrawing
the funds would not be an issue. – In response the Assistant
Director of Regeneration and Property Services advised that the
matter would be investigated further to review the legal framework
and recent correspondence received from Birmingham City
Council. Members would be updated on
progress in this matter.
RESOLVED that the
Levelling-Up Fund Programme – Quarterly Update be
noted.
(During consideration
of this item, Members discussed matters that necessitated the
disclosure of exempt information. It was therefore agreed to move
to exclude the press and public prior to any debate on the grounds
that information would be revealed Information relating to the
financial or business affairs of any particular person (including
the authority holding that information)).