Meeting: 18/05/2009 - Performance Management Board (Item 9)

9 Improvement Plan Exception Report (March 2009) pdf icon PDF 121 KB

Minutes:

The Board considered the Improvement Plan Exception Report for March 2009.

 

RESOLVED:

(a)       that the revisions to the Improvement Plan Exception Report together with the corrective actions being taken be approved;

(b)       that it be noted that for the 102 actions highlighted for March within the plan 80.4% of the Improvement Plan was on target (green), 3.9% was one month behind (amber) and 2% was over one month behind (red). The actions which had been reprogrammed with approval reflected the reprogramming of the town centre actions as a result of issues relating to Parkside, together with the reprogramming of Human Resource actions as a result of Job Evaluation Implementation.