Improvement Plan Exception Report (August 2008)

Meeting: 21/10/2008 - Performance Management Board (Item 60)

60 Improvement Plan Exception Report (August 2008) pdf icon PDF 160 KB

Minutes:

The Board considered the Improvement Plan Exception Report for August 2008, together with the corrective action being taken as set out in appendix 1 to the report. The Assistant Chief Executive undertook to provide members with additional information regarding the situation in respect of the Parkside site. Following discussion it was

 

RESOLVED:

(a)       that the revisions to the Improvement Plan Exception report  together with the corrective action being taken be approved; and

(b)       that it be noted that for the 118 actions highlighted for August 2008 within the plan, 81.4% of the Improvement Plan was on target (green), 3.4% was one month behind (amber) and 14.4% was over one month behind (red).