Issue - items at meetings - Worcestershire Regulatory Services Project Managers Update

Issue - meetings

Worcestershire Regulatory Services Project Managers Update

Meeting: 23/06/2011 - Worcestershire Shared Services Joint Committee (Worcs Shared Services Partnership was dissolved on 31st March 2016. A new partnership was agreed on 1st April 2016 Worcs Regulatory Services Board) (Item 7)

7 Worcestershire Regulatory Services Project Managers Update pdf icon PDF 71 KB

Additional documents:

Minutes:

Mr. I. Edwards, Regulatory Services Project Manager provided Members with a summary of the progress against plans for the period 29th February 2011 to 23rd June 2011.  He informed Members of the key tasks and achievements within each work stream and the revised project end date which had been extended by 3 months.  The original project end date of March 2012 had been moved to June 2012 following the revised dates for the delivery of the transformation work and the subsequent impact this had on the start of the ICT procurement and development process.